Update on I-25/University Project Construction as of January 31, 2020

NOTE: All work is scheduled weather permitting, and is subject to change without notice.

NEW: On Thursday, Feb. 6 from 9 a.m.-3 p.m. Bixby Electric will have one lane closed on southbound I-25 in and near the project area to install fiber.

CONTINUING: Extended through about Friday, Feb. 21, 2020, crews will construct a bridge pier in the median on I-25. During this work, northbound I-25 will have the left lane closed and will be reduced to one lane from about 500 feet north of the I-25/University Bridge to about 1,000 feet south of the Bridge.

Southbound I-25: Two lanes of traffic are open. Traffic south of University Avenue has been shifted about six feet to the left to allow additional room for construction of the new southbound on-ramp.

University Avenue: Two lanes are open in each direction (eastbound and westbound), but the westbound lanes have been shifted to the south near I-25 to allow additional room for crews to work on bridge construction.

MOTORISTS SHOULD USE AN ALTERNATE ROUTE OR EXPECT DELAYS, PARTICULARLY DURING MORNING AND AFTERNOON RUSH HOURS.

Regular work hours are Monday-Friday
7 a.m.-5 p.m. Hours for some activities such as paving will be 8:30 a.m.-4 p